Timeline

CADEMO provides a multi-year time advantage prior to the full-scale commercial development of larger offshore wind projects on the California coast.
    2018
    2019
    2020
    2021
    2022
    2023
    2024
    2025
    2026
    2027
    2028
    2029
    2030
    2031
    2032
    2033
  • Year
  • Sort

2027

Q2 2029
Buffer or delays

If slippage and possible delay of the above milestone

2026

Q3 2026
First Power

CADEMO produces first offshore wind power for California

2025

2025
Build Starts

Fabrication and Construction Begins

2024

2025
Other Permits

Other Necessary Permits secured

TBD
SLC Decision

EIR Certification and Lease Decision by State Land Commissioners

TBD
EIR Issued

Environmental Impact Report (EIR) issued

Q2 2024
Surveys Completed

Site Assessments and Surveys finalized

2023

Q1 2023
Surveys Starting

Site Assessments, Surveys and Environmental Analysis are being undertaken

Q3 2023
Issue NoP

SLC issue of Notice of Preparation with 3rd party environmental consultant

2021

Q3 2021
Approval for EIR

SLC Commissioners accept CADEMO application unanimously to be taken forward into EIR process

2020

Q3 2020
Application Complete

SLC accept CADEMO application for Lease consideration as “Complete”

2019

Q3 2019
Application Submission

Permit application submitted to State Lands Commission (SLC)

2018

Q2 2018
Permit work Start

Permit application work begins