Timeline
CADEMO provides a multi-year time advantage prior to the full-scale commercial development of larger offshore wind projects on the California coast.
- 2018
- 2019
- 2020
- 2021
- 2022
- 2023
- 2024
- 2025
- 2026
- 2027
- 2028
- 2029
- 2030
- 2031
- 2032
- 2033
-
Year
-
Sort
2027
Q2 2029
Buffer or delays
If slippage and possible delay of the above milestone
2026
Q3 2026
First Power
CADEMO produces first offshore wind power for California
2025
2025
Build Starts
Fabrication and Construction Begins
2024
2025
Other Permits
Other Necessary Permits secured
TBD
SLC Decision
EIR Certification and Lease Decision by State Land Commissioners
TBD
EIR Issued
Environmental Impact Report (EIR) issued
Q2 2024
Surveys Completed
Site Assessments and Surveys finalized
2023
Q1 2023
Surveys Starting
Site Assessments, Surveys and Environmental Analysis are being undertaken
Q3 2023
Issue NoP
SLC issue of Notice of Preparation with 3rd party environmental consultant
2021
Q3 2021
Approval for EIR
SLC Commissioners accept CADEMO application unanimously to be taken forward into EIR process
2020
Q3 2020
Application Complete
SLC accept CADEMO application for Lease consideration as “Complete”
2019
Q3 2019
Application Submission
Permit application submitted to State Lands Commission (SLC)
2018
Q2 2018
Permit work Start
Permit application work begins